b2科目四模拟试题多少题驾考考爆了怎么补救
b2科目四模拟试题多少题 驾考考爆了怎么补救

Landsat 8 History

电脑杂谈  发布时间:2016-05-28 16:04:22  来源:网络整理

你是否正在寻找关于landsat的内容?让我把最新的东西奉献给你:




Return to landsat Missions Timeline
landsat 8 History February 11, 2013 - present

Previous |

Landsat 8

Figure 1. landsat 8

Participants

Launch

Watch the launch

Spacecraft

Communications

  • Direct Downlink with Solid State Recorders (SSR)
  • Data rate: 384 Mbps on X-band frequency; 260.92 Mbps on S-band frequency
  • Orbit

    Sensors

    Operational Land Imager (OLI)

  • Nine spectral bands, including a pan band:
  • Thermal Infrared Sensor (TIRS)

  • Two spectral bands:
  • Band 10 TIRS 1 (10.6 - 11.19 µm) 100 m
  • Band 11 TIRS 2 (11.5 - 12.51 µm) 100 m
  • Landsat 8

    Figure 2. OLI and TIRS sensors mounted on LDCM spacecraft. TIRS is covered with gold-hued Multi-layer Insulation, and OLI is covered with white Tedlar insulation.

    Other Characteristics

  • Scene size: 170 km x 185 km (106 mi x 115 mi)
  • Design Life: Minimum of 5 years

  • The Landsat Data Continuity Mission (LDCM) is the next-generation Landsat satellite to ensure the continued acquisition and availability of Landsat-like data beyond the duration of the current landsat missions.

    The LDCM was created in October 2002 to investigate and research options for the most feasible solution to follow the landsat 7 mission. Four options were considered:

    The original LDCM plans called for NASA to purchase data meeting LDCM specifications from a commercially owned and operated satellite system. (Option 2 above) However, after an evaluation of proposals received from industry, NASA cancelled the Request for Proposals in September 2003. In August 2004, a memorandum from the White House Office of Science and Technology Policy (OSTP) directed Federal agencies to place landsat-type sensors on the National Polar-orbiting Operational Environmental Satellite System (NPOESS) platform.

    Following an evaluation of the technical complexity of this task, the strategy was adjusted and on December 23, 2005, a memorandum from the OSTP directed planning to begin for a free-flyer government-only mission, carrying the Operational Land Imager (OLI). In December 2009 a decision was made to add a thermal infrared sensor (TIRS) to the mission payload.

    NASA leads the work on building the flight segment, securing launch services, flight ground systems integration, and conducting on-orbit initialization and verification. After launch checkout processes, the USGS will be responsible for the operations of this mission, which include collecting, archiving, processing, and distributing data products.


    Milestones (Key Decision Points) of LDCM

    To date, a number of Key Decision Points have been achieved:

    September 2008: LDCM KDP-B. This milestone occurred following a successful series of concept and technology development activities whereby the feasibility of the mission concept was measured, system requirements were generated and independently reviewed, and an Initial Confirmation Review was successfully held with NASA Headquarters.

    December 2009: LDCM KDP-C. This milestone occurred following a successful series of system and mission preliminary design activities whereby an initial baseline capable of meeting mission needs (requirements) was established. KDP-C was declared following a successful Mission Confirmation Review held for NASA Headquarters

    October 2011: LDCM KDP-D. This milestone occurred following a successful series of system and mission critical design activities, whereby the detailed design of the entire system was completed and successfully fabricated, including all hardware, software, and operational components. KDP-D was declared following a successful Mission Integration Review held for the LDCM Standing Review Board.

    January 22, 2013: Safety and Mission Success Review (SMSR) at NASA HQ.

    January 23, 2013: Fairing Encapsulation. The LDCM spacecraft was successfully placed into the payload fairing of the Atlas-V rocket that will carry the instrument into space.

    January 25, 2013: Transport to Launch Pad. The payload fairing was transported to Space Launch Complex 3 at Vandenberg Air Force Base in California.

    January 30, 2013: LDCM KDP-E. This milestone occurred following successful system assembly, integration and test. Prior to KDP-E, the project must demonstrate high confidence that the LDCM will be able to meet system requirements, conduct launch and early orbit operations, and meet operational performance expectations. KDP-E will be declared following a successful Flight Readiness Review held for the LDCM Standing Review Board.


    本文来自电脑杂谈,转载请注明本文网址:
    http://www.pc-fly.com/a/ruanjian/article-6659-1.html

    相关阅读
      发表评论  请自觉遵守互联网相关的政策法规,严禁发布、暴力、反动的言论

      • 路魁祯
        路魁祯

        第二我们应该加快自己在南沙的岛礁建设

      • 明神宗
        明神宗

        露出一个明白人的xx

      • 李富松
        李富松

        哈哈

      热点图片
      拼命载入中...